Horizonte Minerals shares crash on revised capital requirements and further nickel mine delays

Horizonte Minerals shares crash on revised capital requirements and further 
nickel mine delays
Horizonte Minerals shares sank on Tuesday after announcing that the capital required to complete construction of its Araguaia nickel project in Brazil has increased to approximately $1 billion, up 87% from previous estimates of $537 million. The revised c

Horizonte Minerals shares sank on Tuesday after announcing that the capital required to complete construction of its Araguaia nickel project in Brazil has increased to approximately $1 billion, up 87% from previous estimates of $537 million.

The revised cost-to-complete (CTC) estimate and construction schedule were prepared by G Mining Services, a mining construction and engineering firm. G Mining estimated the capital needed to finish construction, commission the Araguaia project, and deliver first metal would be around $454 million. When combined with prior spending, this brings the total estimate at completion (EAC) to $1.004 billion.

- Advertisement -

Horizonte said it expects to achieve mechanical completion of Araguaia in the first quarter of 2026 under the revised schedule.

Subscribe to our newsletter

Horizonte Minerals shares were down 59% at the time of writing.

The company appointed Graham Crew as interim Chief Operating Officer to oversee the review process and construction plans. Horizonte also said it is in discussions with major shareholders and lenders to restructure debt facilities and secure full financing for the project.

The news will come as a hammer blow to investors who will now have to wait many years for the first production and face the uncertainty of how Horizonte will actually get there.

- Advertisement -

“Since our last update, a significant volume of work has been completed to develop a new Project Execution Plan, develop a realistic mine plan and business plan, all while continuing to proactively engage with the Company’s cornerstone shareholders, senior lenders, vendors and contractors as well as the community and local authorities,” said interim CEO Karim Nasr.

“While the new Cost-to-Complete is higher than previously announced by the company, it is now built on solid methodologies, which is a testament to the hard work undertaken to date by the whole Horizonte team.”

Similar news
News Archive
  • Phase 3 Scotland
    Phase 3 Scotland
    Phase 3 Scotland: dates rules change as Nicola Sturgeon announces start of next stage of route map out of lockdown
    9 Jul 2020
    1
  • Joe Cullen
    Joe Cullen
    Luke Humphries completes staggering comeback against Joe ...
    30 Dec 2023
    3
  • One NZ
    One NZ
    One NZ reschedules 3G shutdown, plots 2G termination
    5 Apr 2024
    1
  • Scotland v France
    Scotland v France
    Six Nations 2024 LIVE: Scotland v France score and updates as Ben ...
    10 Feb 2024
    16
  • Pricecap regulation
    Price-cap regulation
    Energy Update: Price Cap Hike News Does Not Mean Higher Bills - Ofgem
    24 Nov 2022
    8
  • MC Saatchi
    M&C Saatchi
    M&C Saatchi rejects Vin Murria's sweetened takeover offer valuing the ad company at £254m
    17 May 2022
    9
This week's most popular news